THE TWO NUMBERS, AND WHERE THEY COME FROM
RegLayer: 47+ — a regulatory-information firm counted at least 47 large US data centre projects delayed, withdrawn or blocked since the start of 2026. It calls that a conservative estimate covering only the largest projects.
Bernstein: ~35% — the research firm estimated that only about 35% of the planned US pipeline should be treated as viable.
And a third number nobody quotes: the Financial Times found more than 1,000 US communities attempted moratoriums or restrictions on AI infrastructure this year.
Both figures were reported by the Financial Times on 18 October 2026.
What RegLayer actually is
RegLayer is a regulatory-information firm, not a think tank or an advocacy group. It tracks filings - permits, approvals, interconnection applications and the rest of the paperwork a data centre has to clear before anything is poured. Its count comes from that administrative trail rather than from press releases or sentiment.
That matters for how you read the 47. It is not a forecast and it is not an opinion about whether AI demand is real. It is a count of projects whose paperwork stalled, was withdrawn, or was refused. And RegLayer explicitly describes it as a conservative estimate that covers only the largest projects - so the real number across all project sizes is higher, by an unstated margin.
The second tracker, and why the counts differ
RegLayer is not the only organisation counting. Data Center Watch, a project of the research firm 10a Labs, has been tracking disruption from local opposition specifically.
| Tracker | Count | Period | What it counts |
| RegLayer | 47+ | Since start of 2026 | Large projects delayed, withdrawn or blocked, from regulatory filings |
| Data Center Watch | 75 | Q1 2026 alone | Projects disrupted by local opposition - permitting challenges, moratoriums, withdrawals |
| Data Center Watch | 45 | Q2 2026 (Apr-Jun) | Blocked or delayed, worth nearly $68 billion |
Those numbers look contradictory and are not. They count different things over different windows. RegLayer counts the largest projects across all causes; Data Center Watch counts projects disrupted by local opposition at any size. One is narrower on size, the other narrower on cause.
Do not add the quarters together. Data Center Watch itself warns against treating 75 plus 45 as 120 unique failures - opposition to the same project continues across quarters, so a single contested site can appear in both counts. Anyone reporting a combined figure has misread the methodology.
The two trackers also split on a definition worth keeping straight. Data Center Watch separates blocked - including proposals withdrawn after opposition - from delayed, which can remain active past their original timeline. A delayed project is not a dead one. It is a project whose announced date is now fiction.
What is actually stopping them
The causes are unglamorous and mostly physical:
- Grid interconnection queues. You cannot energise a gigawatt because you signed a lease. Queues run years in several regions.
- Permitting. Local and state approvals, with several states now carrying active moratorium proposals.
- Equipment lead times - transformers and switchgear in particular, which are the long pole on almost every project and have no quick substitute.
- Local opposition. The FT counted over 1,000 communities attempting moratoriums or restrictions this year. That is not a handful of difficult councils; it is a national pattern.
None of these is a demand problem. Compute demand is not in question here. The question is whether the power, the paperwork and the parts arrive in the order the announcements assume.
Named casualties
The FT reporting and its follow-ons name specific pressure points rather than just totals:
- Oracle - several Stargate Project sites, the joint venture with OpenAI and SoftBank, facing schedule delays.
- CoreWeave - the stock fell 23.6% in a week, and one of its corporate bonds has been trading in distressed territory.
- SB Energy (a SoftBank affiliate) and Firmus Grid (Nvidia-backed, Australia) - both delayed or shelved IPO plans.
- Nscale - reporting suggests growing likelihood that Anthropic terminates its $45 billion contract. Treat that as a secondary report rather than a confirmed development; both parties have said nothing, and Bloomberg separately reported on 19 October that the two are in talks for a second deal of similar size. Those two stories cannot both be fully right.
The money underneath
The scale makes the failure rate consequential rather than merely interesting. The US AI infrastructure boom is estimated at roughly $10 trillion. A Brookings paper by Stijn Van Nieuwerburgh of Columbia puts US AI infrastructure spending from 2025 to 2032 at $10.3 trillion, averaging 3.6% of annual GDP.
Van Nieuwerburgh's warning is the structural one: much of the debt financing this sits off balance sheet, and equity value could be wiped out even if cash flow fell only 10%. That is the mechanism by which a delay becomes a default - not a collapse in demand, but a modest shortfall against obligations that were sized for the announced timeline.
The Information has reported predictions that the current field of hundreds of neoclouds consolidates to roughly 7 to 10 within a few years. Cirrascale CEO David Driggers has publicly expected consolidation, naming asset managers and telecom or fibre companies as likely acquirers.
How to read a capacity announcement now
If Bernstein is roughly right, an announced gigawatt is worth about 350 megawatts of expectation. That is the single most useful thing to take from all of this.
It reframes the nuclear restarts from a bullish signal into closer to a necessary one. The Department of Energy confirmed $4.42 billion in loans to restart Palisades (800 MW), the Crane Clean Energy Center (835 MW) and Duane Arnold (615 MW) - 2.25 GW of firm power on sites that already have licences, histories and transmission. Firm power with existing permissions is attractive precisely because the greenfield pipeline keeps slipping.
It also puts the week's enormous contracted figures in proportion. Anthropic reportedly in talks for a second roughly $45 billion commitment. Meta detailing Prometheus, a gigawatt-scale Ohio site eventually targeting a million GPUs. Those are contracts and plans, not delivered capacity, and the gap between the two is what these trackers measure.
FAQ
What is RegLayer?
A regulatory-information firm that tracks filings - permits, approvals and interconnection applications. Its data centre count comes from that administrative record rather than from company statements, which is why it captures stalls that never get announced.
What did RegLayer find about US data centres?
At least 47 large US data centre projects were delayed, withdrawn or had approvals blocked since the start of 2026. RegLayer describes this as a conservative estimate covering only the largest projects, so the figure across all sizes is higher.
What did Bernstein say about the data centre pipeline?
Bernstein estimated in October 2026 that only about 35% of the planned US data centre pipeline should be treated as credible or viable. Both its figure and RegLayer's count were reported by the Financial Times on 18 October 2026.
How do the RegLayer and Data Center Watch numbers fit together?
They measure different things. RegLayer counted 47+ large projects across all causes since January 2026. Data Center Watch, run by 10a Labs, counted 75 projects disrupted by local opposition in Q1 alone, and 45 worth nearly $68 billion in Q2. Data Center Watch warns the quarters should not be summed, because opposition to the same project continues across them.
Why are so many data centre projects stalling?
Four causes dominate: grid interconnection queues, permitting and state-level moratorium proposals, equipment lead times for transformers and switchgear, and local opposition - the Financial Times found more than 1,000 US communities attempting restrictions this year. None of them is a fall in demand for compute.
Does this mean AI demand is collapsing?
No, and nothing in either dataset says that. Both measure supply-side delivery - whether announced capacity can be built, powered and connected on the stated timeline. Demand for compute is not what either firm is assessing.
What is the financial risk if the projects do not get built?
Brookings researcher Stijn Van Nieuwerburgh, of Columbia, notes that much of the financing sits off balance sheet, and that equity value could disappear even on a 10% shortfall in cash flow. The exposure is not a demand collapse; it is obligations sized against announced timelines that then slip.
Which companies are affected so far?
Oracle has schedule delays on several Stargate Project sites. CoreWeave's stock fell 23.6% in a week with a bond trading in distressed territory. SB Energy and Firmus Grid both delayed IPO plans. Nscale has been the subject of conflicting reports - one suggesting Anthropic may terminate its $45 billion contract, another that the two are negotiating a second deal of similar size.